IPS Florida — Weekly Project Briefing

Compass  ·  Lakeland  ·  River Bluff  ·  Bassett  ·  Report date: April 8, 2026  ·  Interest as of bank statement ending 3/31/26
IPS Compass
Construction / Closeout  ·  Report date: April 8, 2026  ·  Interest as of bank statement ending 3/31/26
% spent
96.5%
$33.2M of $34.4M
Unbilled (contracted − spent)
$501,199
Invoices contracted but not yet received
Projected surplus
$230,679
After all anticipated additional costs
$559,939 before anticipated costs
Available to pay unbilled
$1,212,878
Remaining in funding accounts
$1M IPS additional — GL string pending
Section 1 — Budget breakdown by cost category
Cost categoryBudgetContractedSpentUnbilled
(Contracted−Spent)
UncommittedAnticipated addlSurplus / deficit
Professional services$1,688,451$1,685,088$1,662,626$22,462$3,363$0$3,363
RS&H design fee credit / E&O settlement — resolved, final invoice submitted
Construction contracts$12,267,624$12,215,501$11,770,683$444,818$52,123$151,740($99,617)
Gate motors $58K · Intercom $153K · Site lighting $120K · Play area $150K
Other owner impr & fees$853,594$853,594$819,675$33,919$0$0
Client internal costs$18,934,569$18,918,450$18,918,450$0$16,119$0$16,119
Owner's contingency$640,075$640,075$640,075
Total$34,384,313$33,672,633$33,171,435$501,199$711,679$151,740$559,939
Section 2 — Funding source ledger
ⓘ  Available to pay unbilled invoices = cash remaining in the funding account to pay contracted work not yet invoiced. This is not surplus — it is earmarked to fully pay out existing contracts as invoices come in.
Funding sourceAllocatedDrawn / spentAvailable to pay unbilled invoices
Series 2022 Bond 8780 — Principal$22,600,000$22,600,000$0 — fully drawn
Series 2022 Bond 8780 — Interest (thru 3/31/26)$1,230,067$1,229,277$790 — fully applied
Series 2022 Bond 8784 — Principal$9,280,594$9,280,594$0 — fully drawn
Series 2022 Bond 8784 — Interest (thru 3/31/26)$273,652$61,564$212,088
IPS Additional — IPS Regional ($500K)$500,000$0GL pending — Needham / Xiao
IPS Additional — Redirected from Lakeland ($500K)$500,000$0GL pending — board amendment Jan 2025
Total — all funding sources$34,384,313$33,171,435$1,212,878
Section 3 — Anticipated additional costs & projected funds remaining
Status and notes are editable — click to update during the meeting.
DescriptionTypeAmountRunning balanceStatusNotes
Starting uncommitted balance$711,679
Construction contracts
Gate motors (security)cost$58,000$653,679
Intercom systemcost$153,000$500,679
Site lightingcost$120,000$380,679
Play area / equipmentcost$150,000$230,679
Projected funds remaining$230,679
Optional scope — pending campus decision (not included in projected balance above)
Scope itemConstructionSoft costsTotal impactStatusIf approved — funds remaining
Bus canopy$305,276$45,791$351,067on hold($120,388)
Play area / equipment$132,727$19,909$152,636on hold$78,043
Window ballistic film — 1st floorTBDTBDTBDproposals pendingTBD
If bus canopy AND play area both approved($272,624)
Window ballistic film proposals pending — not yet quantified.
Funding history & context
Feb 7, 2025Layne / Rich — $500K IPS Regional funds allocated to Compass shortfall.
Feb 20, 2025Per Adam — Lakeland's $500K redirected to Compass. Board amendment submitted Jan 2025. Total additional = $1M.
Apr 10, 2025Michael Needham + David Xiao coordinating GL account string. Coded to remaining contracts not covered by bond. GL string not yet received — $1M shown as $0 drawn.
IPS Lakeland
Construction / Closeout  ·  Report date: April 8, 2026  ·  Interest as of bank statement ending 3/31/26
% spent
97.7%
$26.3M of $26.9M
Unbilled (contracted − spent)
$28,418
Nearly at closeout
Projected surplus
$570,541
After all anticipated additional costs
$584,541 before anticipated costs
Available to pay unbilled
$612,960
Bond 6541 interest undrawn
Section 1 — Budget breakdown by cost category
Cost categoryBudgetContractedSpentUnbilled
(Contracted−Spent)
UncommittedAnticipated addlSurplus / deficit
Professional services$1,671,408$1,656,647$1,628,228$28,419$14,761$10,000$4,761
Final design fee adjustment + campus work: traffic, irrigation, monument sign
Construction contracts$14,074,623$14,071,998$14,071,998$0$2,625$4,000($1,375)
Final close-out items
Other owner impr & fees$265,733$265,733$265,733$0$0$0$0
Client internal costs$10,337,531$10,337,531$10,337,531$0$0$0$0
Owner's contingency$567,155$567,155$567,155
Total$26,916,451$26,331,909$26,303,491$28,418$584,541$14,000$570,541
Section 2 — Funding source ledger
ⓘ  Available to pay unbilled invoices = cash remaining in the funding account to pay contracted work not yet invoiced. This is not surplus — it is earmarked to fully pay out existing contracts as invoices come in.
Funding sourceAllocatedDrawn / spentAvailable to pay unbilled invoices
Series 2023 Bond 6541 — Principal$25,843,396$25,843,396$0 — fully drawn
Series 2023 Bond 6541 — Interest (thru 3/31/26)$1,073,055$460,095$612,960
Total — all funding sources$26,916,451$26,303,491$612,960
Section 3 — Anticipated additional costs & projected funds remaining
Status and notes are editable — click to update during the meeting.
DescriptionTypeAmountRunning balanceStatusNotes
Starting uncommitted balance$584,541
Professional services
Traffic improvements (extended svcs)cost$6,000$578,541
Irrigation repairscost$4,000$574,541
Construction contracts
Monument sign & site lightingcost$4,000$570,541
Projected funds remaining$570,541
Funding history & context
Feb 20, 2025Original $500K Lakeland allocation redirected to Compass per Adam. Lakeland funded solely by Bond 6541 principal + interest earned.
StatusNo additional funds or GL string required. Project tracking to close with surplus. clean closeout
IPS River Bluff
FY26–27 Summer Work — Pre-Construction  ·  Report date: April 8, 2026
% complete
22.0%
$35,795 spent of $162,650
Unbilled (contracted − spent)
$101,859
Construction underway — not yet invoiced
Projected surplus
$24,996
No anticipated additional costs
Available to pay unbilled
$126,855
Remaining in operating account
Section 1 — Budget breakdown
Cost categoryBudgetContractedSpentUnbilledUncommitted
Professional services$47,650$47,650$35,795$11,855$0
Construction contracts$100,000$90,004$0$90,004$9,996
Other / client internal$0$0$0$0$0
Owner's contingency$15,000$15,000
Total$162,650$137,654$35,795$101,859$24,996
Section 2 — Funding
ⓘ  Available to pay unbilled — not surplus.
Funding sourceAllocatedDrawnAvailable to pay unbilled
Operating Acct
1100-1510-061…FL-JACK-0000
$162,650$35,795$126,855
Total$162,650$35,795$126,855
Section 3 — Forecast
Uncommitted balance$24,996
No anticipated additional costsclean
Projected funds remaining$24,996
IPS Bassett
FY26–27 Summer Work — Pre-Construction  ·  Report date: April 8, 2026
% complete
22.1%
$35,852 spent of $162,052
Unbilled (contracted − spent)
$101,204
Construction underway — not yet invoiced
Projected surplus
$24,996
No anticipated additional costs
Available to pay unbilled
$126,257
Remaining in operating account
Section 1 — Budget breakdown
Cost categoryBudgetContractedSpentUnbilledUncommitted
Professional services$47,052$47,052$35,852$11,200$0
Construction contracts$100,000$90,004$0$90,004$9,996
Other / client internal$0$0$0$0$0
Owner's contingency$15,000$15,000
Total$162,052$137,056$35,852$101,204$24,996
Section 2 — Funding
ⓘ  Available to pay unbilled — not surplus.
Funding sourceAllocatedDrawnAvailable to pay unbilled
Operating Acct
1100-1510-060…FL-JACK-0000
$162,052$35,795$126,257
Total$162,052$35,795$126,257
Section 3 — Forecast
Uncommitted balance$24,996
No anticipated additional costsclean
Projected funds remaining$24,996
2023AB Bond — Project Fund Account
Series 2023AB CAP TRUST AUTHORITY  ·  Project Fund Acct 7080  ·  Balance as of bank statement ending 3/31/26
Do not let this sit unspent — there is a deadline
This is the remaining balance in the 2023AB Bond Project Fund (Acct 7080). The Trust Indenture requires any remaining balance to transfer to the Debt Service Fund at the end of the fifth Bond Year — estimated December 2028 — unless a requisition for outstanding project costs has been submitted. Once it sweeps to debt service it cannot be recovered for capital use.
Confirmed from Morgan Stanley closing memo — Dec 21, 2023
Eligible uses: Acquisition, construction, equipping, and improving of IPS FL educational facilities financed by this bond — Bassett, River Bluff, Hope, Victory, Ignite, Lenox Lane, and Reynolds. Whether Lakeland (Interstate Campus) is also covered requires confirmation. Confirm with Shawn / SLHA.
Spending deadline: End of fifth Bond Year, estimated December 2028. Any undrawn balance sweeps automatically to the Debt Service Fund after that date.
Tax-exempt status (Series 2023A): Confirm with SLHA before any draw if eligibility is in question.
Pending — IPS to confirm with Regions Bank
Shawn Bednasek · Regions Bank · (214) 220-6158 · shawn.bednasek@regions.com
Request: (1) Trust Indenture for the Dec 21, 2023 Capital Trust Authority closing. (2) Loan Agreement — whether completion certificate under Section 3.4 has been filed.
SLHA (IPS outside legal counsel) — confirm eligible use categories and tax compliance before any draw.
Available balance
$354,757.72
As of bank statement 3/31/26
Total interest earned
$91,850.91
Since Dec 2023 closing
Original deposit
$78,131,718
2023A: $78,127,091 · 2023B: $4,628
Spend deadline
Dec 2028
Sweeps to debt service after 5th Bond Year
How the balance arrived here
ItemAmountNotes
Original project fund deposit — Series 2023A + 2023B$78,131,718Dec 21, 2023 closing
Initial loan payoffs — Dec 21, 2023($76,098,254)Bassett, River Bluff, Hope, Victory/Ignite/Lenox Lane, Building Hope, Debt Service, HAK
River Bluff reimbursements — Req 01–25($1,770,558)Apr 2024 – Apr 2025
Interest earned on remaining balance$91,851Jan 2024 – Mar 2026
COI account transfer (Nov–Dec 2025)$5,267Acct 1001037081 closure per Indenture direction + capital gain
Balance as of 3/31/26$354,757.72